Downhill Fireline Construction Checklist

 

Building fireline downhill requires special attention to safety factors because of the potential for rapid uphill fire spread. This Watch Out depicts firefighters building fireline downhill without first mitigating the existing hazards.

9. Building fireline downhill with fire below. Three firefighters use tools to dig fireline down a steep slope covered in grass and brush.  Large flames are below them as the fire burns uphill.

9. Building fireline downhill with fire below.

Read about all 18 Watch Out Situations.

 

Downhill fireline construction is hazardous in steep terrain, fast-burning fuels, or rapidly changing weather. Downhill fireline construction should not be attempted unless there is no tactical alternative. When building downhill fireline:

  • Crew supervisor(s) and fireline overhead must discuss assignments prior to committing personnel. Qualified, responsible overhead individuals such as a Task Force Leader (TFLD) or an Incident Commander Type 4 (ICT4) at minimum, will stay with resources until the job is completed.
  • Decisions about downhill fireline construction will be made only after proposed fireline has been scouted by supervisor(s) of involved crew(s).
  • Lookouts, Communications, Escape Routes, and Safety Zones (LCES) will be coordinated for all personnel involved. This includes verifying:
    • Crew supervisors are in direct contact with lookout(s) who can see the fire.
    • Communication is established between crews.
    • Rapid access to safety zones is ensured in case fire crosses below crews.
  • Direct attack will be used whenever possible; if not possible, the fireline should be completed between anchor points before being fired out.
  • Fireline will not lie in or adjacent to a chute or chimney.
  • Starting point will be anchored for crews building fireline down from the top.
  • Bottom of the fire will be monitored; if the potential exists for the fire to spread, action will be taken to secure the fire edge.
  • Before carrying fire with you, ensure it can be done safely.

 

Last Modified / Reviewed:


Have an idea or feedback?

Share it with the NWCG 6MFS Subcommittee
 


Follow NWCG on X and Facebook
 


 

NWCG Latest Announcements

NWCG Standards for Wildland Fire Chainsaw Operations, PMS 212, and Next Generation Position Task Book for Basic Faller Are Now Available

Date: April 14, 2025
Questions?  Please contact:
Hazard Tree and Tree Felling Subcommittee

The updated NWCG Standards for Wildland Fire Chainsaw Operations, PMS 212, and NWCG Position Task Book for Basic Faller (FAL3), PMS 311-19 are now available.

The NWCG Standards for Wildland Fire Chainsaw Operations, PMS 212 includes position standards designed to be used in conjunction with the Next Generation Position Task Book (Next Gen PTB). The Next Gen PTB for Basic Faller (FAL3) includes an evaluation guide with suggested rating elements to consider when assessing trainees.

References:

NWCG Standards For Wildland Fire Chainsaw Operations, PMS 212

NWCG Position Task Book for Basic Faller (FAL3), PMS 311-119

NWCG Basic Faller (FAL3)

RMC Memo 25-01: Summary of Updates to Safety Officer Positions

Date: April 9, 2025
Questions?  Please contact:
RMC Member Eric Fransted

The Risk Management Committee (RMC) serves as the position steward for all Safety Officer incident positions and continues to improve position standards, training, and naming conventions. The implementation of Complex Incident Management (CIM) required changes to position titles. RMC collaborated with the NWCG Incident Position Standards Committee (IPSC) to propose and implement these updates. 

References:

RMC Memo 25-01: Summary of Updates to Safety Officer Positions 

NWCG Position Catalog

Updated, NWCG Guide to Wildland Fire Origin and Cause Determination, PMS 412

Date: April 8, 2025
Questions?  Please contact:
Wildland Fire Investigation Subcommittee

PMS 412 provides guidance for wildland fire investigations. This guide outlines recommended procedures, practices, techniques, and methods to promote a systematic approach. The last update to this publication was in 2016.

References:

NWCG Guide to Wildland Fire Origin and Cause Determination PMS 412

Updated NWCG Standards for Airtanker Base Operations, PMS 508

Date: March 31, 2025
Questions?  Please contact:
Airtanker Base Operations Unit

The updated NWCG Standards for Airtanker Base Operations (SABO), PMS 508 standardizes operations and procedures at interagency airtanker bases to ensure safe, efficient, and effective operations in support of interagency goals and objectives.

References:

NWCG Standards for Airtanker Base Operations, PMS 508